Case Study


Digicel - Vanuatu
Case Study


Live Sites

Return on Investment Calculator


Solution Certification Case Study

Overview

EnerSys®, Lister Petter and PowerOasis have partnered to produce the first PowerOasis Controller (D) based Certified Reference Solution to reduce diesel consumption on generator powered base stations by at least 50% whilst maximising equipment service life.

The trial was conducted at Lister Petter’s Dursley facility in the UK. The partners started discussions in early 2009 and initiated the project, culminating in a three month trial that completed successfully in December 2009.


Trial Partners


EnerSys

EnerSys® is a global leader in energy storage with an extensive range of quality products backed by more than one hundred years experience of battery manufacturing and innovation. As mobile telephone networks expand into ever more remote regions of our world, many areas have no connection to a main power distribution grid, meaning that 24 hour running on diesel generator power has been the only option. In these increasingly cost and environmentally conscious times, operators are looking to reduce their environmental impact and increase their operating efficiency.

Turning off the generator and using the existing base station backup battery to support the load, then recharging it with the generator whilst also supplying the load appears a straightforward win-win solution. Unfortunately, many existing backup power batteries were never designed with this heavy cyclic, “Hybrid power” demand in mind.

EnerSys® has responded to the new demand with new technologies and new application research. The results are products developed specifically with cyclic applications in mind, and with engineering applications information to support systems design for success. The most critical consideration is reliable and consistent recharging of the battery, to ensure optimum discharge performance and life.

For more information please visit: www.enersys-emea.com/reserve/hybrid


Lister Petter

Lister Petter have operations in the UK, USA, France, India and China, giving the company global reach and ensuring that its customers are never too far from their expertise whenever they need diesel or gas engine technology.

From its roots over 140 years ago to today, producing advanced diesel and gas-powered engines for a wide range of applications, Lister Petter have consistently set the standard in innovation, quality and reliability. With millions of Lister Petter engines in use globally, the environments and uses that they have been put to is remarkable.

Equipment “downtime” can be very expensive for phone operators, so reliable power supply is essential. Lister Petter engines have a reputation for reliably, providing base load and stand-by power to the telecommunications sector throughout Africa, The Middle East and India.

With the number of base stations globally that are powered by diesel generators set to increase by 50% over the next four years and base station loads continuing to fall due to improvements in technology and design, diesel generators are destined to be operated continuously at more inefficient loads, leading to generator damage, decreased service life and increased servicing visits.

For more information please visit: http://telecommunications.lister-petter.co.uk


Objectives

The primary trial objectives were to:

Prove systems interoperability and solution operation

Verification of consistent battery cycling throughout the trial and battery capacity at the end of the trial

Fine tune PowerOasis Controller (D) configuration parameters

Generate operational data to validate benefit claims

Create a Solution Blueprint to include a comprehensive component list

Publish installation, commissioning, support and maintenance guides

Install remote monitoring for customer demonstrations


Test Load – 1550W

A 1.55kW resistive load was used to simulate a mobile base station telecommunications equipment load.


Key Components

This table lists the main components included in the trial.

Component

Manufacturer

Make & Model

Configuration

Diesel
Generator
Lister Petter LLD140A Running at 1800rpm, 60Hz, 3 phase, developing 10.6kWe

Batteries EnerSys SBS EON 190F Arranged in six 48V strings, total capacity 1140AH

Rectifier Benning TEBECHOP 3000HD Three rectifiers, 9KW total output at 92% nominal efficiency

Power
Controller
PowerOasis PowerOasis Controller (D) 44% battery maximum depth of discharge

Remote
Monitoring
PowerOasis PowerOasis Manager Via SMS/GPRS modem



Rectifier: Benning TEBECHOP 3000 HD

With the TEBECHOP 3000 HD rectifier modules, redundant 48 V DC power systems with system ratings between 6 kW and 70 kW can be realised. The ultra compact dimensions of the 3000 HD rectifier with a power density of approximately 1 kW/dm3 is the result of intensive research and development to optimise components and airflow inside the high power section of the rectifier. Tolerant of harsh environmental conditions the rectifiers operate from –33 °C up to +75 °C ambient temperature.


Batteries: EnerSys SBS EON 190F

The batteries used in the trial are the EnerSys® SBS EONs with superior bulk charge capabilities and ideally suited to running a diesel generator for the shortest time possible to achieve full state of charge. The PowerSafe SBS EON TechnologyTM retains the benefits typically associated with EnerSys® Thin Plate Pure Lead (TPPL) technology (long life, high energy density, superior shelf life, etc.), but they also deliver exceptional cyclic performance in both float and fast charge applications, even in the hottest and harshest operating environments.

Extensive testing has shown that in traditional float cyclic applications PowerSafe SBS EON Technology surpasses the excellent performance of standard PowerSafe SBS designs, typically delivering a 33% increase in the number of cycles during evaluation to international benchmark standards.



Generator: Lister Petter LLD140A

Equipment “downtime” can be very expensive for telecommunications and mobile phone operators, so reliable power supply is essential. Lister Petter engines have an enviable and long established reputation for reliably providing base load and stand-by power to the telecommunications sector throughout Africa, The Middle East and India.


Test Results

The following data illustrates the results after 83 days of testing. The ‘before’ figures show the metrics when a generator is used to power the load and the ‘after’ figures show the metrics after the PowerOasis Controller (D) based solution is introduced.


Criteria

Before

After

Comments

Cumulative Generator Runtime 1992 Hours 560 Hours  72% reduction in
 generator run time

Daily Generator Runtime 24 Hours 6.5 Hours
Cumulative Diesel Consumption 2681 Litres 1263 Litres  53% reduction in
 fuel consumption

Daily Diesel Consumption 32.3 Litres 15.2 Litres
Battery Cycles N/A 83  4.8 years battery life

Battery Depth of Discharge N/A 44%

Note:
The above figures are conservative and represent testing with new equipment in a controlled environment. With retrofit field deployments the savings will likely be greater due to the presence of larger generators, which are often in poor condition and typically adding 20% to the ‘before’ fuel consumption.


Battery Management

The following chart from the PowerOasis Manager illustrates the charging profile for the batteries over a 5-day period.

Battery Management

The battery doesn’t drop below 56% state of charge and always returns to 100% state of charge at the end of each cycle, which adheres to EnerSys recommendations and leads to a predicted battery life of 4.8 years.

PowerOasis Solutions flyer
Download the
PowerOasis Solutions
flyer 


PowerOasis Solutions Certification Case Study
Download the PowerOasis Solutions Certification
Case Study 







The cost of delivering high volumes of diesel to remote off-grid locations was predicted to be exceptionally high



Although the capital cost of deploying the green power solutions was higher than the diesel generators, the operating costs are substantially lower without compromising the quality of power availability


The purpose designed telecoms-grade PowerOasis controller features an integrated wind turbine power controller offering higher efficiency, 1+1 power and control system redundancy for high availability, and optimised battery conditioning algorithms
layout spacer imageTerms of Use  layout spacer image  Privacy Policylayout spacer image© Copyright PowerOasis 2012. All rights reservedlayout spacer image